In Gantt Charts, Progress Indicators and Budget Warnings
Now in TopLeft Gantt charts, task bars indicate the progress of the work. This helps project managers understand their projects and react quickly to problems.
The colouring of the bar indicates the progress:
The dark part of the bar indicates how many hours have been logged relative to the work's budget. For example, this would indicate about 80% of the budget had been used:
When work exceeds the budget, it is shown in red:
This applies to both tickets, tasks, and projects. If a ticket, task, or project has no budget, no coloring is applied.